Optimas International partnered with a global manufacturer of battery systems to recover a stalled battery line after structural fasteners from its incumbent supplier began failing in production and were found to be below the required property class. Working within the OEM’s restricted source list, Optimas International sourced a compliant, correctly specified replacement part and delivered it in less than half the industry standard
lead time. The line restarted with zero fastener failures and without the need for costly airfreight.

Situation

The customer manufactures battery trays for a major automotive OEM. The fasteners used in these joints are safety-critical and must maintain the required clamp load reliably throughout service.

Production was disrupted when structural fasteners from the incumbent supplier began failing during production and were found to be below the required property class. The customer therefore faced two immediate priorities: restore production quickly and establish whether joints already assembled with the suspect fasteners remained compliant and fit for purpose.

Challenge

Production rework: Failed screws had to be extracted and the affected joints reworked, manually. This was a slow process that disrupted
production stations operating to tight takt times.

Resource-intensive containment: Containment, sorting and evidence of conformity required significant input from engineering and quality teams, diverting resources from other priorities.

Restricted sourcing: OEM approval limited the customer to a small number of qualified sources, reducing the options available for an urgent
replacement.

Compressed lead time: The typical lead time for the part in the correct specification was 16-22 weeks, but the customer needed supply within
8-10 weeks. Following the standard procurement route would therefore have left the production exposed for several more months.

Solution

Optimas International developed a supply strategy that worked within the customer’s existing OEM approval requirements while reducing the 16-22 week standard lead time to less than 10 weeks.

Identifying an approved source: Before quoting, Optimas International’s engineers checked the customer’s OEM approval requirements and traced the fastener’s approved source. Rather than offer an equivalent that would need a deviation or further approval, they found an approved German manufacturer able to make it to the required specification and property class. This ensured compliant supply from the outset, with no risk of an unapproved part entering a safety-critical application.

Running supply and testing in parallel: Optimas International placed the production order ahead of completion of the customer’s testing window, allowing supply and validation activities to progress in parallel. By taking on the inventory risk, Optimas International removed a significant period of waiting time from the programme. This enabled a fastener with a standard 16-22 week lead time to be supplied within
the customer’s 8-10 week recovery window.

Delivering without air freight: The approved manufacturer was located within road freight range of the customer’s sites in Austria and Hungary. Optimas International arranged dedicated express road transport. The consignment remained intact and fully traceable from dispatch
through to goods-in, avoiding the additional cost, emissions and handling associated with airfreight.

Results

Optimas International restored production with a compliant fastener, delivering the required property class within the customer’s 8-10 week requirement, more than 50% faster than the standard 16-22 week lead time. Production restarted with zero fastener failures, resolving the issue at source rather than relying on ongoing containment or deviation.

Download case study

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.